Sharon City School District STEAM

Project Overview

Location: Sharon, PA
Statistics:
  • Project Size: 18,568 sq. ft.
  • Total Construction Budget: $4.1 million
  • NEIS Contract: 450,000
Products
  • CiF Premium Educator Series Red Oak Wood Casework
  • CiF Apex Air Fume Hoods
  • Durcon Black Epoxy Countertops
Project Delivery Team:
  • Architect: Eckles Architecture
  • General Contractor: Hudson Construction
Manufacturing Partner(s):

Project Summary


Sharon City School District renovated the science classrooms within their Middle and High School facilities to accommodate STEAM curriculum. The renovation will provide students will a collaborative environment for learning and discovery. Northeast installed CiF Lab Solutions’ Educator Series premium Tier 1 wood casework. The Educator Series incorporates integral end panels and full flush overlay 1/16” reveals. Red oak veneer with a clear finish and vertical grain match, for consistent uniformity in grain and color, complete the space.